Hi All-
The power shutdown this morning went well. John C and I
shutdown all Athena systems and Macs in 2-032 by 6:50am
and all were backup by the specified 7:45am. There were
no machine fatalities to speak of. The alarm for 11-135
went into alarm and CP showed up, we have reset. Also
Kim all systems in 11-135 looked ok asof 7:20am.
All in all it went well.
JJ