Approved: Bldg. 38 - All - Chilled Water Shutdown (CyPress Design
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Fri Aug 16 12:29:09 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: "achow@mit.edu" <achow@MIT.EDU>,
"fletch1@EECS.MIT.EDU"
<fletch1@EECS.MIT.EDU>,
"sbleeb@mit.edu" <sbleeb@MIT.EDU>,
"OPS RM Campus
Services Main" <rm-mcs@MIT.EDU>,
"burkhart@mtl.mit.edu"
<burkhart@mtl.mit.edu>,
"diadiuk@mit.edu" <diadiuk@MIT.EDU>,
"mcgrath@mtl.mit.edu" <mcgrath@mtl.mit.edu>,
"agallant@mit.edu"
<agallant@MIT.EDU>,
"airyan@MIT.EDU" <airyan@MIT.EDU>,
MIT Schedules Office
<schedules@MIT.EDU>,
"jdaley@nano.mit.edu" <jdaley@nano.mit.edu>,
"wgibbs@rle.mit.edu" <wgibbs@rle.mit.edu>,
"amcgurl@RLE.MIT.EDU"
<amcgurl@rle.mit.edu>,
"mondol@mit.edu" <mondol@MIT.EDU>,
"heatherg@mit.edu"
<heatherg@MIT.EDU>,
"shutdowns@mit.edu" <shutdowns@MIT.EDU>,
"whomeyer@mit.edu" <whomeyer@MIT.EDU>,
"ksemerj@mit.edu" <ksemerj@MIT.EDU>,
Gary Saffie <gsaffie@plant.mit.edu>,
Ops RM Shutdown <rm-shutdown@MIT.EDU>, DOF EHS <dof-ehs@MIT.EDU>,
"cp-command@mit.edu" <cp-command@MIT.EDU>,
"safety@mit.edu" <safety@MIT.EDU>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@MIT.EDU>,
"Ops Custodial Admin & Support
Staff" <cust-staff@MIT.EDU>
CC: "jennygar@mit.edu" <jennygar@MIT.EDU>, "pisanin@mit.edu" <pisanin@MIT.EDU>
Date: Fri, 16 Aug 2013 12:29:01 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C76EA845@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Chilled Water shutdown (CyPress Design Eng Studio renovation project) is for bldg. 38 - All on Tuesday, August 20, 2013 from 4:00am til 8:00am is for your information. Any questions please contact Billy Homeyer x8-0432.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: August 20, 2013
Day: Tuesday
Time: 4:00am 8:00am
Building(s): 38
Room(s): All
System: chilled water, supply cooling
Duration: 4 hrs
Reason:
We request a bldg 38-partial chilled water shutdown from 4 AM to 8 AM on Tuesday morning, August 20th, 2013 for AHC Mechanical (Al Cairns 781-844-7817) to tie-in new fan coil unit service for the 5th floor from a main chilled water riser as part of the 5th floor CyPress Design Eng Studio project by Acella Construction (Marcilio Silva 781-733-1248). Nicole Pisani 5-5157 and Biss Teelucksingh 2-5972 are the MIT project managers.
AH1-bsmt, AH2-fls 1-6 north, AH3-fls 1-6 south, AH4-MBE Lab are not affected however 38-301 and any other equipment cooling will be affected. Bldg 38 fan coil units will also not be cooling during the shutdown. AH1, 2, 3 provide the overhead cooling from the diffusers in the ceilings.
Effect:
Loss of chilled water and supply cooling for the duration of this shutdown.