Approved: Bldg. 1 - Air Handler #5 (PM #720240) and Air Handler #6
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Fri Aug 9 09:53:11 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: "mbuehler@MIT.EDU" <mbuehler@mit.edu>,
"patdixon@mit.edu"
<patdixon@mit.edu>,
"jgermain@mit.edu" <jgermain@mit.edu>,
"ghavidel@MIT.EDU"
<ghavidel@mit.edu>,
"savicki@mit.edu" <savicki@mit.edu>,
"OPS RM Campus
Services Main" <rm-mcs@mit.edu>,
"sbghosh@MIT.EDU" <sbghosh@mit.edu>, "fenner@mit.edu" <fenner@mit.edu>,
MIT Schedules Office <schedules@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
Gary Saffie <gsaffie@plant.mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>, DOF EHS <dof-ehs@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>,
"mcweeney@mit.edu"
<mcweeney@mit.edu>
Date: Fri, 9 Aug 2013 09:53:06 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C687EE7C@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Air Handler #5 and #6 shutdown is for bldg. 1 - All on Saturday, August 10, 2013 from 6:00am - 10:30am is for your information. Air Handler #6 affects 1-115, Air Handler #5 affects 1-050, first and second floor classrooms. Any questions please contact Joe McWeeney x3-8731.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: August 10, 2013
Day: Saturday
Time: 6:00am - 10:30am
Building(s): 1
Room(s): 115, 050 - first and second floor classrooms
System: supply ventilation/cooling
Duration: 6:00am - 10:30am/ 4 1/2 hrs.
Reason:
This is for preventative maintenance inspection, v-belt and air filter changes.
Air Handler #6 affects 1-115, Air Handler #5 affects 1-050, first and second floor classrooms.
Start time for AH#5 is 6:00am Finish time for AH5 8:30am Start time for AH#6 is 8:30am Finish time for AH6 10:30am
Effect:
Loss of supply ventilation and cooling for the duration of this shutdown.