Approved: Bldg. E25- Basement - All Steam, Process Hot Water,

daemon@ATHENA.MIT.EDU (Jennifer Garland)
Wed Aug 7 14:25:58 2013

From: Jennifer Garland <jennygar@plant.mit.edu>
To: "jdoughty@mit.edu" <jdoughty@mit.edu>, "swade@mit.edu" <swade@mit.edu>,
        "macdonaj@mit.edu" <macdonaj@mit.edu>,
        "craigp@MIT.EDU" <craigp@mit.edu>,
        "OPS RM Campus Services East" <rm-ecs@mit.edu>,
        Ops Custodial Admin & Support
 Staff <cust-staff@mit.edu>,
        "bengel@mit.edu" <bengel@mit.edu>, "rdfadel@MIT.EDU" <rdfadel@mit.edu>,
        "tquinn@mit.edu" <tquinn@mit.edu>, "ninadm@mit.edu" <ninadm@mit.edu>,
        Michael Smith <masmith@mit.edu>, "brig@med.mit.edu" <brig@med.mit.edu>,
        MIT Schedules Office
	<schedules@mit.edu>,
        "scottide@MIT.EDU" <scottide@mit.edu>,
        "heatherg@mit.edu" <heatherg@mit.edu>,
        "shutdowns@mit.edu"
	<shutdowns@mit.edu>,
        David Hingston <dhingsto@plant.mit.edu>,
        Ops RM Shutdown
	<rm-shutdown@mit.edu>, DOF EHS <dof-ehs@mit.edu>,
        "cp-command@mit.edu"
	<cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>,
        Operators
	<Operators@plant.mit.edu>,
        "DOF Customer Service Center" <dof-csc@mit.edu>,
        "Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>,
        "mmcorrei@mit.edu"
	<mmcorrei@mit.edu>
Date: Wed, 7 Aug 2013 14:25:51 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C6790AF4@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved All Steam, Process Hot Water, Heating Hot Water, Supply Heating Shutdown is for bldg. E25 - basement (animal quarters) is on Thursday, August 8, 2013 from 8:00am - 10:00am is for your information.  Any questions please contact Mike Correira x8-9174.


Thank you,

Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: August 8, 2013
Day: Thursday
Time: 8:00am - 10:00am 
Building(s): E25
Room(s): basement
System: all steam, process hot water, heating hot water, supply heating
Duration: 2 hrs
Reason: 
This is to make repairs to steam leak in this system.

Effect: 
Loss of all steam, process hot water, heating hot water, supply heating for the duration of this shutdown. 