[171374] in Hotline Meeting
CANCELLED: Bldg. 10 - Air Handler #6 (PM #731205) and Air Handler
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Wed Aug 7 14:19:17 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: Jim Harrington <lordjim@mit.edu>, "laugh@mit.edu" <laugh@mit.edu>,
"jgk@mit.edu" <jgk@mit.edu>,
OPS RM Campus Services Main <rm-mcs@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
"gearin@mit.edu"
<gearin@mit.edu>, "wangal@mit.edu" <wangal@mit.edu>,
"jschuler@mit.edu"
<jschuler@mit.edu>,
Michael Smith <masmith@mit.edu>, "mleen@mit.edu"
<mleen@mit.edu>,
"dstidsen@mit.edu" <dstidsen@mit.edu>,
"carleton@mit.edu"
<carleton@mit.edu>,
"smuto@MIT.EDU" <smuto@mit.edu>, "esdeb@mit.edu"
<esdeb@mit.edu>,
"emmarogers@mit.edu" <emmarogers@mit.edu>,
"annm@mit.edu"
<annm@mit.edu>, "kates@mit.edu" <kates@mit.edu>,
MIT Schedules Office
<schedules@mit.edu>,
"kyegian@MIT.EDU" <kyegian@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
Gary Saffie <gsaffie@plant.mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>,
"mcweeney@mit.edu"
<mcweeney@mit.edu>
Date: Wed, 7 Aug 2013 14:19:11 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C6790AE1@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following CANCELLED Air Handler #6 and #5 shutdown is for bldg 10 - first and second floors is on Saturday, August 10, 2013 from 6:00am - 10:30am is for your information. Any questions please contact Joe McWeeney x3-8731.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: August 10, 2013/// CANCELLED
Day: Saturday
Time: 6:00am - 10:30am///CANCELLED
Building(s): 10
Room(s): bldg.
System: supply vent/cooling
Duration: 6:00am - 2:00pm
Reason:
This is for an preventative maintenance inspection/v-belts/filter replacement/air filter changes. Air Handler #6 (PM 731205) affects 10-115; Air Handler #5 (PM 730240) affects 10-050, first and second floor classrooms.
Start time: 6:00am for Air Handler #5 --- End Time: 8:30am for Air Handler #5
8:30am for Air Handler #6 --- End Time: 10:30am for Air Handler #6
Effect:
Loss of supply ventilation and cooling for the duration of this shutdown.