[171369] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 24 - All Normal Building Power 208V/120V Shutdown

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed Aug 7 12:40:51 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <jcombst@MIT.EDU>
Date: Wed, 7 Aug 2013 12:40:46 -0400
Message-ID: <D7A1B6A88B964D189C029E9D4D808686@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Normal Building Power 208V/120V Shutdown is for bldg. 24 - all on Tuesday, August 13, 2013 from 12:01am til 6:00am is for your information and approval.  Any questions please contact Billy Homeyer x8-0432.


Would  you please let us know if this does or does not have your approval.

Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: August 13, 2013
Day: Tuesday
Time: 12:01am - 6:00am
Building(s): 24
Room(s): All
System: normal building power, access controls, computers, telephones, lighting, chilled water, heating hot water, supply vent/cooling/heating, gen exhaust/hood exhaust
Duration: 12:01am - 6:00am - 6 hrs
Reason: 
We request bldg 24-DP1 normal 208V/120V bldg power shutdown from 12:01 AM to 6 AM on Tuesday morning, August 13th, 2013 for Bennett Electric to install a 125A circuit breaker in DP1 and tie-in power for a new 24-114 computer power panel as part of the 24-4th floor LNS renovation project by Barr and Barr Builders (John Bidgood 508-686-0870). Sudy Nally 8-8010 and Jennifer Combs 3-7671 are the MIT project managers.
DP1 feeds the following panels/equipment

The bldg 24-elevator

Normal power to the telephone switch room (ATS will switch to the emergency power) 

6th floor power panels CP6-2 and CP6-3; all of 6th floor affected

Ground and 1st floor panels CP0-1 and CP1-1; Ground floor hallway outlets/lighting (includes the soda and snack machines) and all of the 1st floor

24-032 panel P-032-B-1; all the 24-032 computer power

24-011 panel P-011; all the power to grad student office 011

Ground floor panel CP0-1; also serves some power in 032 suite offices and some hallway power


Effect: 
Loss of all normal building power for the duration of this shutdown. 