[171323] in Hotline Meeting
Approved Bldg. 46 - All, Lab Compressed Air Shutdown
daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue Aug 6 11:50:49 2013
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "graham@mit.edu" <graham@mit.edu>, "abm@mit.edu" <abm@mit.edu>,
"Gerry
Desmond" <gdesmond@mit.edu>,
"handsom@MIT.EDU" <handsom@mit.edu>,
"hegarty@mit.edu" <hegarty@mit.edu>,
"rqsmith@mit.edu" <rqsmith@mit.edu>, "bbrown@mit.edu" <bbrown@mit.edu>,
"cgallo34@mit.edu" <cgallo34@mit.edu>,
"jstatile@mit.edu" <jstatile@mit.edu>,
"macdonaj@mit.edu" <macdonaj@mit.edu>,
"rmarini@mit.edu" <rmarini@mit.edu>, "mmpatt@mit.edu" <mmpatt@mit.edu>,
"OPS
RM Campus Services Main" <rm-mcs@mit.edu>,
Ops CSG All <csg-all@mit.edu>, "gwolf@mit.edu" <gwolf@mit.edu>,
"gillooly@MIT.EDU" <gillooly@mit.edu>,
"liberman@mit.edu" <liberman@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"k_brown@MIT.EDU" <k_brown@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu"
<cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
Operators
<Operators@plant.mit.edu>,
DOF Customer Service Center <dof-csc@mit.edu>,
"Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>
CC: "ajsilva@mit.edu" <ajsilva@mit.edu>, "mwelter@mit.edu" <mwelter@mit.edu>
Date: Tue, 6 Aug 2013 11:50:19 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C6790271@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved lab compressed air shutdown for Bldg. 46 - All, on Wednesday, August 7, 2013, 6:00am - 7:00am, is for your information. Any questions, please contact Joe Silva, x3-1602.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: August 7, 2013
Day: Wednesday
Time: 6:00am - 7:00am
Building(s): 46
Room(s): All
System: Lab Compressed Air
Duration: 1 hour
Reason:
repair of pressure gauge and valve on tank
Effect:
Loss of compressed lab air for the duration of the shutdown.