Approved Bldg. 18 - 4th Floor, Process Chilled Water Shutdown

daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue Aug 6 11:46:43 2013

From: Janine Findlay <jfindlay@plant.mit.edu>
To: Ops RM Shutdown <rm-shutdown@MIT.EDU>,
        "cp-command@mit.edu"
	<cp-command@MIT.EDU>,
        "safety@mit.edu" <safety@MIT.EDU>,
        Operators
	<Operators@plant.mit.edu>,
        DOF Customer Service Center <dof-csc@MIT.EDU>,
        "Ops Custodial Admin & Support Staff" <cust-staff@MIT.EDU>,
        "shutdowns@mit.edu" <shutdowns@MIT.EDU>,
        "jdoughty@mit.edu"
	<jdoughty@MIT.EDU>,
        "lippard@mit.edu" <lippard@MIT.EDU>, "swade@mit.edu"
	<swade@MIT.EDU>,
        "rjwilk@mit.edu" <rjwilk@MIT.EDU>,
        OPS RM Campus Services
 East <rm-ecs@MIT.EDU>,
        Ops CSG All <csg-all@MIT.EDU>, "gillooly@MIT.EDU"
	<gillooly@MIT.EDU>,
        "scottide@MIT.EDU" <scottide@MIT.EDU>,
        "heatherg@mit.edu"
	<heatherg@MIT.EDU>,
        "k_brown@MIT.EDU" <k_brown@MIT.EDU>,
        "monaglek@MIT.EDU"
	<monaglek@MIT.EDU>
CC: "ajsilva@mit.edu" <ajsilva@MIT.EDU>, "mgodding@mit.edu" <mgodding@MIT.EDU>
Date: Tue, 6 Aug 2013 11:46:31 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C679026C@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved process chilled water shutdown for Bldg. 18 - 4th Floor, on Wednesday, August 7, 2013, 7:00am - 1:00pm, one shaft at a time, two hours per shaft, three shafts total, is for your information.  Any questions, please contact Joe Silva, x3-1602.

Thank you,

Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilties
x3-6381

Type: Normal
Date: August 7, 2013
Day: Wednesday
Time: 7:00am - 1:00pm
Building(s): 18
Room(s): 4th Floor
System: Process Chilled Water
Duration: 6 hours
Reason: 
to repair strainers and install isolation valves

Effect: 
Loss of process chilled water for the duration of each 2 hour shaft shutdown.