[171306] in Hotline Meeting
Bldg. E14-1st fl. Fire Alarm System Shutdown (w/live audible testing 6AM-8AM)
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue Aug 6 08:51:11 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <kims1@plant.mit.edu>
Date: Tue, 6 Aug 2013 08:51:08 -0400
Message-ID: <DB19B6C5F40A4548BACD0FD5B9BF2F35@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Fire Alarm System Shutdown is for bldg. E14-1st fl. on Wednesday, August 7, 2013 from 6:00am - 10:00am and then on Thursday, August 8, 2013 from 6:00am - 8:00am for live audible testing is for your information and approval. Any questions please contact Billy Homeyer x8--0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: August 7, 2013
Day: Wednesday
Time: 6:00am til 10:00am (Thu) - 6:00am - 8:00am
Building(s): E14
Room(s): 1st fl.
System: fire alarm
Duration: 6:00am til 10:00am (Thu) - 6:00am - 8:00am
Reason:
We request a bldg E14-Lobby area 1st floor, fire alarm shutdown from 6 AM to 10:00 AM on, Wednesday 7th to relocate fire alarm devices in building E14 1st floor Lobby area and conduct brief *live audible independent 3rd party testing of the bldg E14 fire alarm system*, on Thursday 8th at 6:00 am to 8:00 am to be witnessed by DEI Systems (Phil Deneault 508-341-4184) to test relocated fire alarm devices installed by MacNichol Electric. This renovation is with Bond Brothers (Michael Bean 617-913-4100). (Kim Sutherland 781-426-6731) is the MIT project manager.
Effect:
Loss of fire alarms for the duration of this shutdown.