[171305] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. E25-6th fl. Fire Alarm Shutdown (*live audible testing on 8/7 and 8/8)

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue Aug 6 08:13:57 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <biss@MIT.EDU>
Date: Tue, 6 Aug 2013 08:13:52 -0400
Message-ID: <A10141FBFA59473FA5764AE55970D49D@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Fire Alarm Shutdown (*live audible testing on 8/7 and 8/8) is for bldg. E25- 6th fl on Wednesday, August 7, 2013 til Thursday, August 8, 2013 from 6:00am til 7:30am both days. Any questions please contact Billy Homeyer x8-0432.


Would you please let us know if this does or does not have your approval.

Thank you,

Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: August 7, 2013
Day: Wednesday
Time: 6:00am - 7:30am
Building(s): E25
Room(s): 6th fl.
System: fire alarm
Duration: 6:00am - 7:30am
Reason: 
We request bldg E25-6th floor fire alarm shutdowns as follows;from 6 AM to 2 PM on Wednesday, August 7th, 2013, Simplex (Rich Perron 781-603-7799) will program HOA switches for the new exhaust fans and from 6 AM to 7:30 AM, we will conduct a *live audible 1st party test of the new E25-6th floor fire alarm devices*.   On Thursday,  August 8th, 2013 from 6 AM to 7:30 AM, JMBCo (Rich Cucchi 617-522-6800) will conduct a *live audible 3rd party test of the E25-6th floor fire alarm system* as part of the Prof. McGee lab cleanroom renovation project by DC Beane (Ryan Kucinski 617-997-9498).  Biss Teelucksingh 2-5972 and Paul Murphy 4-6361 are the MIT project managers on behalf of Billy Homeyer.

Effect: 
Loss of fire alarms for the duration of this shutdown. 

home help back first fref pref prev next nref lref last post