[171300] in Hotline Meeting
Bldg. 2- All and Bldg. 4-269T,4-070 thru 082 - Normal Building Power (all 480V/208V/120V bldg power) Shutdown
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Aug 5 14:21:11 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <mdeluga@MIT.EDU>
Date: Mon, 5 Aug 2013 14:21:06 -0400
Message-ID: <C43AC2386A00425199419CF784B919DA@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Normal Building Power (all 480V/208V/120V bldg power) Shutdown is for bldg. 2 - All and bldg. 4-269T,4-070 thru 082 on Saturday, August 10, 2013 from 12:01AM - 12:00PM (noon) is for your information and approval. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: August 10, 2013
Day: Saturday
Time: 12:00AM - 12:00PM (noon)
Building(s): 2-All and bldg. 4
Room(s): bldg. 2 all - bldg. 4 - 269T, 070 thru 082
System: access controls, bldg power, computer, telephones, lighting, chilled water,heating hot water, supply vent/cooling/heating, exhaust general/hood
Duration: 12 hrs.
Reason:
We request a bldg 2-all normal bldg power shutdown, all 480V/208V/120V normal power from 12:01 AM to 12 noon on Saturday, August 10th, 2013 for Bennett Electric (John Shaw 617-293-4806) to install 6 new circuit breakers for 4 new power panels and re-feeding two other existing panels as part of the Chemistry renovation project by Bond Brothers (Jesse Conklin 617-938-4175). Marty Deluga 4-5081 and Joe Collins 3-3621 are the MIT project managers.
All of bldg 2 including active labs will be affected via loss of lab/computer power or loss of services (heating/cooling/supply-exhaust air etc). This schedule calls for those labs to be functional again at noon on Saturday 8/10.
Bldg 4 tel/data closet 4-269T and the 4-070 and 082 Music and Theatre Arts suites will also be without power during the 12 hour shutdown period.
480V panel DPH2G1 gets a 225A cb for a new panel
208V panel MDP-B we terminate the new Ceyer lab bldg 2 feeder
208V panel DPL2G1 gets five 225A cb's and we tie-into a spare 400A cb
X-ray lab 2-325 power will be refed from one of the new power panels
Effect:
Loss of normal building power for the duration of this shutdown.