[171217] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 18 - 4th Floor, Process Chilled Water Shutdown Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Aug 1 15:05:50 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <ajsilva@MIT.EDU>, <mgodding@MIT.EDU>
Date: Thu, 1 Aug 2013 15:05:42 -0400
Message-ID: <B6FE408EF249427F957D5BA2AC6F714E@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following process chilled water shutdown request for Bldg. 18 - 4th Floor, on Wednesday, August 7, 2013, 7:00am - 1:00pm, one shaft at a time, two hours per shaft, three shafts total, is for your information and response.  Any questions, please contact Joe Silva, x3-1602.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilties
x3-6381

Type: Normal
Date: August 7, 2013
Day: Wednesday
Time: 7:00am - 1:00pm
Building(s): 18
Room(s): 4th Floor
System: Process Chilled Water
Duration: 6 hours
Reason: 
to repair strainers and install isolation valves

Effect: 
Loss of process chilled water for the duration of each 2 hour shaft shutdown.

home help back first fref pref prev next nref lref last post