Bldg.62 - 5th Floor, Fire Protection Water Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed Jul 31 13:39:39 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <cgilbert@MIT.EDU>, <billvit@MIT.EDU>
Date: Wed, 31 Jul 2013 13:39:32 -0400
Message-ID: <FD636FF8B78D4EC0B74BC6F59DB3E0A2@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following fire protection water shutdown notification for Bldg.62 -5th floor, on Thursday, August 1, 2013 from 6:00am-3:30pm is for your information. No response is required to this notification. Any questions, please contact Billy Homeyer X.8-0432
We appreciate your patience while the repairs/renovations are in progress.
Thank you,
Chris Gilbert
Operations Center
The Safety Office will be advised of this and notify the Fire Department.
Type: Normal
Date: August 1, 2013
Day: Thursday
Time: 6:00am-3:30pm
Building(s): 62
Room(s): 5th floor
System: Fire Protection Water
Duration: 9.5 hours
Reason:
As a precautionary measure as part of cutting the existing wire lathe and plaster.
Effect:
Loss of fire protection water in area during duration of shutdown.