[171199] in Hotline Meeting
Bldg.E14-151 Smoke Detector Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed Jul 31 13:39:00 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jwestgat@MIT.EDU>, <kims1@MIT.EDU>
Date: Wed, 31 Jul 2013 13:38:55 -0400
Message-ID: <19E8EAE30D774573A22F0899C33F1278@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Smoke Detector, shutdown notification for Bldg.E14-151 on Thursday, August 1, 2013 and Friday, August 2, 2013 from 6:00am-3:00pm is for your information. No response required to this notification. Any question please contact Billy Homeyer 8-0432.
We appreciate your patience while the repairs/renovations are in progress.
Thank you
Jessica Westgate
Operations Center
Type: Normal
Date: August 1, 2013
Day: Thursday
Time: 6:00am-3:00pm
Building(s): E14
Room(s): 151
System: Smoke Detectors
Duration: 9 hours/day
Reason:
For construction dust and all general construction-related activities.
Effect:
Loss of smoke detectors in the area during the duration of the shutdown.