[171115] in Hotline Meeting
Bldg. 32 - Dreyfoos All, Exhaust Fans 4 and 1 - General and Toilet Exhaust Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jul 29 13:20:40 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <kdiggans@MIT.EDU>
Date: Mon, 29 Jul 2013 13:20:29 -0400
Message-ID: <999EABBE174843A8A48195B87742137C@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following exhaust fans 4 and 1 - general and toilet exhaust for Bldg. 32 - Dreyfoos All, on Thursday, August 1, 2013, 6:00am - 2:00pm, is for your information and response. Any questions, please contact Karen Semerjian, x3-6217.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: August 1, 2013
Day: Thursday
Time: 6:00am - 2:00pm
Building(s): 32
Room(s): Dreyfoos All
System: Exhaust Fans 4 and 1 - General and Toilet Exhaust
Duration: 8 hours
Reason:
We request bldg 32D-EF4 & EF1 (toilet exhaust) shutdown from 6 AM to 2 PM on Thursday, August 1st, 2013 to power these fans (breakers are locked-out) to install permanent power to equipment and remove the old temporary power - (NOTE: these are exhaust fans and are continuously running and will not need to test prior to shutting them down) as part of the 32-roof repair project by Consigli Construction (Carlin Grenier 508-458-0590). Keith Diggans 4-6174 is the MIT project manager on behalf of Billy Homeyer.
Effect:
Loss of general and toilet exhaust for the duration of the shutdown.