[171114] in Hotline Meeting
Bldg. 32 - Stairwell Pressurization Systeam and Dreyfoos Elevator Machine Room - Supply Fan 8, 8A, and ACCU Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jul 29 13:15:39 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <kdiggans@MIT.EDU>
Date: Mon, 29 Jul 2013 13:15:28 -0400
Message-ID: <FC9BA1D50A7846F7BE5E11A639C9109C@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following supply fan 8 and 8A and air conditioning unit for Bldg. 32 - Stairwell Pressurization Systeam and Dreyfoos Elevator Machine Room, on Wednesday, July 31, 2013, 6:00am - 2:00pm, is for your information and response. Any questions, please contact Karen Semerjian, x3-6217.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: July 31, 2013
Day: Wednesday
Time: 6:00am - 2:00pm
Building(s): 32
Room(s): Stairwell Pressurization Systeam and Dreyfoos Elevator Machine Room
System: Supply Fan 8, 8A, and ACCU
Duration: 8 hours
Reason:
We request bldg 32-SF8A, SF8 & ACCU (Dreyfoos elevator machine room AC) shutdowns from 6 AM to 2 PM on Wednesday, July 31st, 2013 to power fans (breakers are locked out) to install permanent power to equipment & disconnect and to remove old temporary power (NOTE: may need to put fans in machine room to move air so equipment does not overheat) as part of the 32-roof repair project by Consigli Construction (Carlin Grenier 508-509-2935), WEH for Keith Diggans 4-6174
Effect:
Loss of Dreyfoos stairwell pressurization and elevator machine room supply ventilation for the duration of the shutdown.