[171053] in Hotline Meeting
Approved: Bldg. 1- All Fire Alarm Shutdown/3rd Party Live Audible
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Fri Jul 26 13:24:37 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: "mbuehler@MIT.EDU" <mbuehler@MIT.EDU>,
"patdixon@mit.edu"
<patdixon@MIT.EDU>,
"jgermain@mit.edu" <jgermain@MIT.EDU>,
"ghavidel@MIT.EDU"
<ghavidel@MIT.EDU>,
"savicki@mit.edu" <savicki@MIT.EDU>,
"OPS RM Campus
Services Main" <rm-mcs@MIT.EDU>,
"sbghosh@MIT.EDU" <sbghosh@MIT.EDU>, "fenner@mit.edu" <fenner@MIT.EDU>,
MIT Schedules Office <schedules@MIT.EDU>,
"shutdowns@mit.edu" <shutdowns@MIT.EDU>,
"whomeyer@mit.edu"
<whomeyer@MIT.EDU>,
"ksemerj@mit.edu" <ksemerj@MIT.EDU>,
Ops RM Shutdown
<rm-shutdown@MIT.EDU>, DOF EHS <dof-ehs@MIT.EDU>,
"cp-command@mit.edu"
<cp-command@MIT.EDU>,
"safety@mit.edu" <safety@MIT.EDU>,
Operators
<Operators@plant.mit.edu>,
DOF Customer Service Center <dof-csc@MIT.EDU>,
"Ops Custodial Admin & Support Staff" <cust-staff@MIT.EDU>
CC: "jennygar@mit.edu" <jennygar@MIT.EDU>, "healyb@mit.edu" <healyb@MIT.EDU>
Date: Fri, 26 Jul 2013 13:23:57 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C63A9058@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Fire Alarm Shutdown/3rd Party Live Audible Testing is for bldg. 1 - All on Sunday, August 4, 2013 at 11:00pm til Friday, August 9, 2013 at 7:00am is for your information. Any questions please contact Billy Homeyer x8-0432.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: August 4, 2013
Day: Sunday<
Time: 11:00pm (Sun) - 7:00am (Fri)
Building(s): 1
Room(s): All
System: Fire Alarm
Duration: 11:00pm (Sun) - 7:00am (Fri)
Reason:
We request bldg 1-all fire alarm shutdowns from 11 PM to 7 AM on Sunday evening, August 4th through Thursday, August 8th, 2013 (into Friday morning) to conduct *3rd party live audible testing of the bldg 1 fire alarm system* and to be witnessed by DEI Systems (Phil Deneault 508-341-4184) as part of the bldg 1 life-safety fire alarm upgrade project by Tishman Construction (Dennis Ryan 617-594-0664). Brian Healy 8-8565 is the MIT project manager on behalf of Billy Homeyer.
Effect:
Loss of fire alarms for the duration of this shutdown.