[170853] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 32- Exhaust Fan #7 Shutdown (also servies loading dock) 32 - roof repair project

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jul 18 15:03:24 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <kdiggans@MIT.EDU>
Date: Thu, 18 Jul 2013 15:03:17 -0400
Message-ID: <7BDA03620BB3420BAA0F6383CB3914E2@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Exhaust Fan #7 Shutdown (also servies loading dock) 32 - roof repair project is for bldg. 32 on Monday, July 22, 2013 from 3:00am - 7:00am is for your information and approval.  Any questions please contact Billy Homeyer x8-0432.


Would you please let us know if this does or does not have your approval.

Thank you,

Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: July 22, 2013
Day: Monday
Time: 3:00am - 7:00am
Building(s): 32
Room(s): bldg.
System: exhaust general
Duration: 3:00am - 7:00am - 4 hrs.
Reason: 
We request a bldg 32-EF7 (also serves loading dock) from 3 AM to 7 AM on Monday, July 22nd, 2013 to relocate the fan for re-roofing under it as part of the 32-roof repair project by Consigli Construction (Carlin Grenier 508-458-0590).  Keith Diggans 4-6174 is the on behalf of Billy Homeyer.

Effect: 
Loss of general exhaust for the duration of this shutdown. 

home help back first fref pref prev next nref lref last post