[170605] in Hotline Meeting
RE: *Extended Bldg. 46 - All, Normal Building Power Shutdown Request - *to include Saturday, 7/20
daemon@ATHENA.MIT.EDU (Ramika Smith)
Tue Jul 9 11:54:17 2013
From: "Ramika Smith" <rqsmith@MIT.EDU>
To: "'Janine Findlay'" <jfindlay@plant.mit.edu>, <graham@MIT.EDU>,
<abm@MIT.EDU>, "'Gerry Desmond'" <gdesmond@MIT.EDU>,
<macdonaj@MIT.EDU>, "'OPS RM Campus Services Main'" <rm-mcs@MIT.EDU>,
"'Ops CSG All'" <csg-all@MIT.EDU>, <liberman@MIT.EDU>,
<heatherg@MIT.EDU>, <shutdowns@MIT.EDU>,
"'Ops RM Electrical Controls Team'" <rm-elecctl@MIT.EDU>,
<rlucas@MIT.EDU>, <dcrovo@MIT.EDU>, <whomeyer@MIT.EDU>,
<ksemerj@MIT.EDU>, "'Ops RM Shutdown'" <rm-shutdown@MIT.EDU>
Cc: <sudy@MIT.EDU>
In-Reply-To: <4EEA516695C10541B7CB963FF54A56AF13C4966713@dof-exchmbx01.facilities.ms.mit.edu>
Date: Tue, 9 Jul 2013 11:54:12 -0400
Message-ID: <003f01ce7cbc$903f5a90$b0be0fb0$@edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Language: en-us
Content-Transfer-Encoding: 8bit
There is an experiment that will be completed on Saturday July 20th and they
can not afford to shutdown their power until Sunday July 21st, we can not
approve this.
Ramika Smith
Admin Ast. to Building Manager
46-1145/(617) 324-5178
*************************************
REQUEST for REPAIRS
Gerry Desmond – Building Manager
Email: 46maintenance@mit.edu
or call Assistant, Ramika at x4-5178
-----Original Message-----
From: Janine Findlay [mailto:jfindlay@plant.mit.edu]
Sent: Tuesday, July 09, 2013 11:48 AM
To: graham@mit.edu; abm@mit.edu; Gerry Desmond; rqsmith@mit.edu;
macdonaj@mit.edu; OPS RM Campus Services Main; Ops CSG All;
liberman@mit.edu; heatherg@mit.edu; shutdowns@mit.edu; Ops RM Electrical
Controls Team; rlucas@mit.edu; dcrovo@mit.edu; whomeyer@mit.edu;
ksemerj@mit.edu; Ops RM Shutdown
Cc: sudy@mit.edu
Subject: *Extended Bldg. 46 - All, Normal Building Power Shutdown Request -
*to include Saturday, 7/20
The following *extended normal building power shutdown request for Bldg. 46
- All, on Tuesday, July 2, 2013, 4:00am - 12:00pm and Wednesday, July 3,
2013, 4:00am - 6:00am, *to also include Saturday, July 20, 2013, 6:00am -
6:00pm, is for your information and response. Any questions, please contact
Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: July 2, 2013
Day: Tuesday
Time: 4:00am - 12:00pm (7/2); 4:00am - 6:00am (7/3)
Building(s): 46
Room(s): All
System: Normal Building Power
Duration: 8 hours/2 hours
Reason:
We request bldg 46 normal bldg power shutdowns, 480V panel D42C1 located in
2148E from 4 AM to 12 noon on Tuesday, July 2nd for Suburban Electric (Don
Ouellette 781-760-5422) to install 800A and 2A circuit breakers to serve the
new MRI; and 480V panel D42C located in 2201u/m from 4 AM to 6 AM on
Wednesday, July 3rd, 2013 to change out a 20A circuit breaker (fed a Leibert
unit) to a 60A breaker in order to serve the new 1150 MRI room chiller and
as part of the 46-1150 MRI Lab renovation project by Wise Construction
(Chris Luongo 781-389-5749). Sudy Nally 8-8010 is the MIT project manager.
Panel D42C1 feeds panel L42C, rodent mag lab transformer, rodent mag lab
humidifier, panel D22C, panel D21C, panel L41C and the rodent lab magnet
transformer.
Panel D42C feeds lab vacuum pumps, lab and control air compressors, an
animal bedding vacuum system, VFDs for pumps 5 and 6, CAC Leibert units 1-4,
motor control center 2C, panel P22C and FCU 5.
*Extended - Dear all, I need to extend the 480V panel D42C1 shutdown to
include Saturday, July 20th, 2013 from 6 AM to 6 PM in order to pull the
wiring for the 800A service for the new MRI lab 1150 and tie-into the new
800A circuit breaker that was installed on Tuesday 7/9. The effects of this
shutdown will be identical to the Tuesday 7/2 power shutdown.
Effect:
Loss of normal building power, heating hot water, chilled water, supply
cooling air, compressed control air, compressed lab air, and lab vacuum for
the duration of the shutdown.