*Extended Bldg. 46 - All, Normal Building Power Shutdown Request -
daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue Jul 9 11:48:36 2013
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "graham@mit.edu" <graham@mit.edu>, "abm@mit.edu" <abm@mit.edu>,
"Gerry
Desmond" <gdesmond@mit.edu>,
"rqsmith@mit.edu" <rqsmith@mit.edu>,
"macdonaj@mit.edu" <macdonaj@mit.edu>,
OPS RM Campus Services Main
<rm-mcs@mit.edu>,
Ops CSG All <csg-all@mit.edu>, "liberman@mit.edu"
<liberman@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
Ops RM Electrical Controls Team
<rm-elecctl@mit.edu>,
"rlucas@mit.edu" <rlucas@mit.edu>, "dcrovo@mit.edu"
<dcrovo@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"ksemerj@mit.edu"
<ksemerj@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>
CC: "sudy@mit.edu" <sudy@mit.edu>
Date: Tue, 9 Jul 2013 11:48:28 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C4966713@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following *extended normal building power shutdown request for Bldg. 46 - All, on Tuesday, July 2, 2013, 4:00am - 12:00pm and Wednesday, July 3, 2013, 4:00am - 6:00am, *to also include Saturday, July 20, 2013, 6:00am - 6:00pm, is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: July 2, 2013
Day: Tuesday
Time: 4:00am - 12:00pm (7/2); 4:00am - 6:00am (7/3)
Building(s): 46
Room(s): All
System: Normal Building Power
Duration: 8 hours/2 hours
Reason:
We request bldg 46 normal bldg power shutdowns, 480V panel D42C1 located in 2148E from 4 AM to 12 noon on Tuesday, July 2nd for Suburban Electric (Don Ouellette 781-760-5422) to install 800A and 2A circuit breakers to serve the new MRI; and 480V panel D42C located in 2201u/m from 4 AM to 6 AM on Wednesday, July 3rd, 2013 to change out a 20A circuit breaker (fed a Leibert unit) to a 60A breaker in order to serve the new 1150 MRI room chiller and as part of the 46-1150 MRI Lab renovation project by Wise Construction (Chris Luongo 781-389-5749). Sudy Nally 8-8010 is the MIT project manager.
Panel D42C1 feeds panel L42C, rodent mag lab transformer, rodent mag lab humidifier, panel D22C, panel D21C, panel L41C and the rodent lab magnet transformer.
Panel D42C feeds lab vacuum pumps, lab and control air compressors, an animal bedding vacuum system, VFDs for pumps 5 and 6, CAC Leibert units 1-4, motor control center 2C, panel P22C and FCU 5.
*Extended - Dear all, I need to extend the 480V panel D42C1 shutdown to include Saturday, July 20th, 2013 from 6 AM to 6 PM in order to pull the wiring for the 800A service for the new MRI lab 1150 and tie-into the new 800A circuit breaker that was installed on Tuesday 7/9. The effects of this shutdown will be identical to the Tuesday 7/2 power shutdown.
Effect:
Loss of normal building power, heating hot water, chilled water, supply cooling air, compressed control air, compressed lab air, and lab vacuum for the duration of the shutdown.