[170584] in Hotline Meeting
Approved Bldg. 6C - All and Bldg. 4, Room 007 - Normal 208V
daemon@ATHENA.MIT.EDU (Janine Findlay)
Mon Jul 8 15:05:18 2013
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
Ops RM Electrical Controls Team
<rm-elecctl@mit.edu>,
"rlucas@mit.edu" <rlucas@mit.edu>, "dcrovo@mit.edu"
<dcrovo@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"ksemerj@mit.edu"
<ksemerj@mit.edu>, Jim Harrington <lordjim@mit.edu>,
"laugh@mit.edu"
<laugh@mit.edu>, "graham@mit.edu" <graham@mit.edu>,
"abm@mit.edu"
<abm@mit.edu>, "kdonn@mit.edu" <kdonn@mit.edu>,
"tommyl@mit.edu"
<tommyl@mit.edu>, "myersm@MIT.EDU" <myersm@mit.edu>,
"jdoughty@mit.edu"
<jdoughty@mit.edu>,
"swade@mit.edu" <swade@mit.edu>, "rjwilk@mit.edu"
<rjwilk@mit.edu>,
"mdemaine@mit.edu" <mdemaine@mit.edu>,
"Bales@mit.edu"
<Bales@mit.edu>,
"acalogge@mit.edu" <acalogge@mit.edu>,
"slipnosk@mit.edu"
<slipnosk@mit.edu>,
"relices@MIT.EDU" <relices@mit.edu>,
"jlmorgan@mit.edu"
<jlmorgan@mit.edu>,
"sharonp@mit.edu" <sharonp@mit.edu>,
"OPS RM Campus
Services Main" <rm-mcs@mit.edu>,
Ops Custodial Admin & Support Staff
<cust-staff@mit.edu>,
Ops CSG All <csg-all@mit.edu>, "mbj@mit.edu"
<mbj@mit.edu>,
"xingxingb@hotmail.com" <xingxingb@hotmail.com>,
"blayne@mit.edu" <blayne@mit.edu>,
"chris@bostonmoores.com"
<chris@bostonmoores.com>,
"pbhouk@gmail.com" <pbhouk@gmail.com>, Gerry Hughes
<ghughes@mit.edu>,
"Tarky@mit.edu" <Tarky@mit.edu>,
"help@math.mit.edu"
<help@math.mit.edu>,
"pelletier@math.mit.edu" <pelletier@math.mit.edu>,
"mottley@mit.edu" <mottley@mit.edu>,
"carleton@mit.edu" <carleton@mit.edu>, "smuto@MIT.EDU" <smuto@mit.edu>,
"gillooly@MIT.EDU" <gillooly@mit.edu>,
"cubstead@MIT.EDU" <cubstead@mit.edu>,
"cmodica@mit.edu" <cmodica@mit.edu>, "morley@mit.edu" <morley@mit.edu>,
"momeara@mit.edu" <momeara@mit.edu>, "yopak@MIT.EDU" <yopak@mit.edu>,
"wayneb@mit.edu" <wayneb@mit.edu>,
"MIT
Schedules Office" <schedules@mit.edu>,
"scottide@MIT.EDU" <scottide@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"chibcha@MIT.EDU" <chibcha@mit.edu>, "zqueen@mit.edu" <zqueen@mit.edu>,
"vdavenport@MIT.EDU" <vdavenport@mit.edu>,
"k_brown@MIT.EDU" <k_brown@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu"
<cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
Operators
<Operators@plant.mit.edu>,
DOF Customer Service Center <dof-csc@mit.edu>,
"Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>
CC: "mdeluga@mit.edu" <mdeluga@mit.edu>
Date: Mon, 8 Jul 2013 15:04:58 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C49662D9@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved normal building power shutdown for Bldg. 6C - All (normal lighting affected only), and Bldg. 4, Room 007 (temp loss of power to lab affected), on Tuesday, July 9, 2013, 2:00am - 6:00am, is for your information. Any questions, please contact Billy Homeyer, x8-0432.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: July 9, 2013
Day: Tuesday
Time: 2:00am - 6:00am
Building(s): 6C and 4
Room(s): 6C - All and 4, Room 007
System: normal building power (temp loss of power to lab 4-007 and lighting only for 6C)
Duration: 4 hours
Reason:
We request a bldg 6C-208V normal power panel DPLIG1 shutdown from 2 AM to 6 AM on Tuesday morning, July 9th, 2013.
This panel is located in high voltage room 6C-0006AE and Bennett Electric (John Shaw 617-763-2840) needs to install a new 400A circuit breaker for back-up power the Prof Ceyer Lab on the 1st floors of bldg 2 and 6. This back-up power ties into a manual transfer switch in HV room 2-017E.
During this shutdown bldg 6C will be without normal lighting.
Lab 4-007 will temporarily go on generator power. Power panels A and B will both be powered and 4-007 will lose power only momentarily at the beginning and end of this shutdown.
This shutdown is being conducted as part of the bldg 2-Chemistry renovation project by Bond Brothers (Jesse Conklin 617-936-4175) and Marty Deluga 4-5081 and Joe Collins 3-3621 are the MIT project managers.
Panels fed out of DPLIG1 are 4-007 LPL4007A and B (DMSE Battery Lab) and 6C lighting panels LPL6G1, 2, 5, 6, 7, 8 and 9 - PLIG1, CPLI11, PLIG2, and CPLIG1.
Effect:
During this shutdown bldg 6C will be without normal lighting.
Lab 4-007 will temporarily go on generator power. Power panels A and B will both be powered and 4-007 will lose power only momentarily at the beginning and end of this shutdown.