[170419] in Hotline Meeting
Approved - Bldg. 37-3rd fl. Normal Building Power Shutdown
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Wed Jun 26 10:43:02 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: "pbauer@mit.edu" <pbauer@mit.edu>, "oconaill@mit.edu" <oconaill@mit.edu>,
"DICKP@MIT.EDU" <DICKP@mit.edu>, "alz@MIT.EDU" <alz@mit.edu>,
"swade@mit.edu"
<swade@mit.edu>, "asbosh@MIT.EDU" <asbosh@mit.edu>,
"craigp@MIT.EDU"
<craigp@mit.edu>,
OPS RM Campus Services Main <rm-mcs@mit.edu>,
"Ops
Custodial Admin & Support Staff" <cust-staff@mit.edu>,
"ois-plant-notify@mit.edu" <ois-plant-notify@mit.edu>,
"jmdefand@SPACE.MIT.EDU" <jmdefand@SPACE.MIT.EDU>,
"ralf@space.mit.edu"
<ralf@SPACE.MIT.EDU>,
"src@mit.edu" <src@mit.edu>,
"bsurette@space.mit.edu"
<bsurette@SPACE.MIT.EDU>,
MIT Schedules Office <schedules@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"alvarso@mit.edu" <alvarso@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
Gary Saffie <gsaffie@plant.mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>, DOF EHS <dof-ehs@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>,
Steven Gilligan
<sgilliga@plant.mit.edu>
Date: Wed, 26 Jun 2013 10:42:56 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C4590289@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Normal Building Power Shutdown is for bldg. 37 - 3rd fl. on Thursday, June 27, 2013 from 5:00am - 7:00am is for your information. Any questions please contact Steve Gilligan x3-8079.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: June 27, 2013
Day: Thursday
Time: 5:00am - 7:00am
Building(s): 37
Room(s): 3rd fl. random (fan coils 301/311, lights 310, recept. 301, 311, 315, 331
System: normal building power shutdown
Duration: 5:00am - 7:00am 2 hrs
Reason:
This is to tie in new circuits for this area.
Effect:
Loss of normal building power for the duration of this shutdown.