[170418] in Hotline Meeting
Bldg. 4-All Domestic and Lab Process Hot and Cold Water, DI Water (bldg. 2 Chemistry renovation project, 4-classrms portion)
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed Jun 26 10:07:31 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <mdeluga@MIT.EDU>
Date: Wed, 26 Jun 2013 10:07:24 -0400
Message-ID: <A02CC6BCBAC64D68A5ACCC36FE39D254@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Domestic and Lab Process Hot and Cold Water, DI Water (bldg. 2 Chemistry renovation project, 4-classrms portion) is for bldg. 4-all on Thursday, June 27, 2013 from 5:00am - 6:00am is for your information and approval. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: June 27, 2013
Day: Thursday
Time: 5:00am - 6:00am
Building(s): 4
Room(s): All
System: hot/cold domestic water, hot/cold lab process, de-ionized water
Duration: 5:00am - 6:00am
Reason:
We request bldg 4-all domestic, lab process and DI water shutdowns, from 5 AM to 6 AM on Thursday morning, June 27th, 2013 to cut/cap abandoned services that run thru the 4-270/370 classrooms and as part of the 4 classrooms portion of the 2-Chemistry renovation project by Bond Brothers (Jesse Conklin 617-938-4175). Marty Deluga 4-5081 and Joe Collins 3-3621 are the MIT project managers.
Effect:
Loss of hot/cold domestic water, hot/cold lab process, de-ionized water for the duration of this shutdown.