[170089] in Hotline Meeting
*Cancelled - Bldg. 46 - All, Compressed Lab Air Shutdown Request -
daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue Jun 11 14:48:22 2013
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "graham@mit.edu" <graham@mit.edu>, "abm@mit.edu" <abm@mit.edu>,
"Gerry
Desmond" <gdesmond@mit.edu>,
"rqsmith@mit.edu" <rqsmith@mit.edu>,
"macdonaj@mit.edu" <macdonaj@mit.edu>,
OPS RM Campus Services Main
<rm-mcs@mit.edu>,
Ops CSG All <csg-all@mit.edu>, "liberman@mit.edu"
<liberman@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
Ops RM Shutdown
<rm-shutdown@mit.edu>
CC: "ajsilva@mit.edu" <ajsilva@mit.edu>, "mgodding@mit.edu" <mgodding@mit.edu>
Date: Tue, 11 Jun 2013 14:48:12 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C2EEAF4E@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following compressed lab air shutdown request for Bldg. 46 - All, on Wednesday, June 12, 2013, 6:00am - 7:00am, has been CANCELLED and will be rescheduled at a later time. Any questions, please contact Joe Silva, x3-1602.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: June 12, 2013 **CANCELLED**
Day: Wednesday
Time: 6:00am - 7:00am
Building(s): 46
Room(s): All
System: Compressed Lab Air
Duration: 1 hour
Reason:
tie-in of a test port on the compressed air tank for department of public safety - gauge test port
**CANCELLED** - we were not able to get full approval from occupants and there this request is being cancelled and will be rescheduled at a later time. Thank you.
Effect:
Loss of compressed lab air for the duration of the shutdown.
**CANCELLED** - will be rescheduled