[170088] in Hotline Meeting
Approved - Bldg. W71- Domestic Hot Water Shutdown
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Tue Jun 11 14:36:36 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: "tommyl@mit.edu" <tommyl@mit.edu>, "myersm@MIT.EDU" <myersm@mit.edu>,
"OPS RM Campus Services West" <rm-wcs@mit.edu>,
"src@MIT.EDU" <src@mit.edu>, "hmgr@mit.edu" <hmgr@mit.edu>,
"kcn@mit.edu" <kcn@mit.edu>, "mwhelan@mit.edu"
<mwhelan@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
"alegere@mit.edu"
<alegere@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>, DOF EHS
<dof-ehs@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@mit.edu>,
"Ops Custodial Admin & Support
Staff" <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>,
David Hingston
<dhingsto@plant.mit.edu>
Date: Tue, 11 Jun 2013 14:36:30 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C2EEAF26@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Domestic Hot Water Shutdown is for Bldg. W71 - All on Wednesday, June 12, 2013 from 9:00am - 1:00pm is for your information. Any questions please contact Dave Hingston x4-4548.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: June 12, 2013
Day: Wednesday
Time: 9:00am - 1:00pm
Building(s): W71
Room(s): bldg.
System: domestic hot water
Duration: 9:00am - 1:00pm
Reason:
This is to make repairs to leaking hot water tank.
Effect:
Loss of domestic hot water for the duration of this shutdown.