[169988] in Hotline Meeting
Bldg. W20-Exhaust Fan 11, hood exhaust fan (Cambrdige Grill) Shutdown
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jun 6 13:13:35 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <healyb@MIT.EDU>
Date: Thu, 6 Jun 2013 13:13:14 -0400
Message-ID: <362FB0F35EAA452EB71BCECF7460328E@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Exhaust Fan 11 and Hoot Exhaust Fan (Cambridge Grill) Shutdown is for bldg.W20-Cambridge Grill on Monday, June 17, 2013 from 9:00PM til Tuesday, June 18, 2013 at 5:00am is for your information and approval. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: June 17, 2013
Day: Monday
Time: 9:00PM (Mon) - 5:00AM (Tue)
Building(s): W20
Room(s): bldg. - Cambridge Grill
System: exhaust fan 11, hood exhaust fan (Cambridge Grill)
Duration: 9:00PM (Mon) - 5:00AM (Tue)
Reason:
We request EF11-711122 hood exhaust fan shutdown in bldg W20-Cambridge Grille from 9 PM to 5 AM on Monday, June 17th, 2013 (into Tuesday morning) to replace roof fan (NOTE: the fan & disconnects are located in room 546) for
One Call Ventilation to weld restaurant kitchen hood exhaust ductwork as part of the W20 kitchen exhaust systems upgrade project by Elaine Construction (Robin Lorscheider 781-727-8834). Brian Healy 8-8565 is the MIT project manager on behalf of Billy Homeyer.
Effect:
Loss of hood exhaust fan #11 (PM#711122) for the duration of shutdown.