Bldg. 2- All Chilled Water Shutdown (bldg. 4-2 fl smoke detectors)

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jun 6 08:18:07 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <mdeluga@MIT.EDU>
Date: Thu, 6 Jun 2013 08:16:58 -0400
Message-ID: <40A85508B56D464FB95E40E74E1D235B@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Chilled Water Shutdown is for bldg. 2 - ALL (bldg. 4 - 2nd fl. smoke detectors) is on Saturday, June 8, 2013 forom 6:00am - 10:00PM is for your information and approval.  Any questions please contact Billy Homeyer x8-0432.


Would you please let us know if this does or does not have your approval.


Thank you,

Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: June 8, 2013
Day: Saturday
Time: 6:00AM - 10:00PM
Building(s): 2
Room(s): ALL
System: chilled water, supply cooling, smokes
Duration: 6:00AM - 10:00PM
Reason: 
We request a bldg 2-all critical chilled water shutdown and a bldg 4-2nd floor south smoke detector shutdown each from 6 AM to 10 PM on Saturday, June 8th for JC Higgins to reconfigure the 2-2nd floor 6" supply and return mains that are crossconnected and as part of the bldg 2 Chemistry renovation project by Bond Brothers, Jesse Conklin 617-938-4175). Marty Deluga 4-5081 and Joe Collins 3-3621 are the MIT project managers.



Effect: 
Loss of chilled water for the duration of this shutdown. 