[169863] in Hotline Meeting
Bldg. E17 & E18 - All Normal 208&120 Volt Power Shutdown
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri May 31 10:12:16 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <rlucas@MIT.EDU>
Date: Fri, 31 May 2013 10:12:07 -0400
Message-ID: <7BB29BF006834D1AA7302F73184E7E0D@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Normal 208/120 Volt Power Shutdown is for bldgs. E17 & E18 starting on Thursday, June 20, 2013 at 11:00pm til Friday, June 21, 2013 at 7:00am is for your information and approval. Any questions please contact Rich Lucas 617-324-6801.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: June 20, 2013
Day: Thursday
Time: 11:00pm (Thu) - 7:00am (Fri)
Building(s): E17 & E18
Room(s): All
System: emergency gen, bldg power,elevators, computers, telephone, lighting, corridors/stairs, chilled wtr, cond. water, supply ventilation,cooling,heating, gen exhaust/toilet, conden return, fire alarm
Duration: 11:00pm (Thu) - 7:00am (Fri)
Reason:
A shutdown is requested for all normal 208 Volt power in buildings E18 & E17. This work will be done at night and it is pre-approved by John MacDonald. I will be replacing the Main circuit breaker and a PM of the remaining switchgear.
Schedule:
Thursday night 11:00 PM, June 20 to Friday morning 7:00 AM, June 21.
Emergency Power will not be affected.
AHU3 & 6 will NOT be affected - they are on a different source of power.
Effect:
Loss all normal 208/120 volt power to these buildings for the duration of this shutdown.