[169862] in Hotline Meeting
Approved Bldg. NW35 - All, Air Handlers 1 through 5 Shutdown
daemon@ATHENA.MIT.EDU (Janine Findlay)
Fri May 31 09:53:24 2013
From: Janine Findlay <jfindlay@plant.mit.edu>
To: Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu"
<cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
Operators
<Operators@plant.mit.edu>,
DOF Customer Service Center <dof-csc@mit.edu>,
"Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>, Ops CSG All <csg-all@mit.edu>,
"OPS
RM Campus Services West" <rm-wcs@mit.edu>,
"src@MIT.EDU" <src@mit.edu>, "colins@mit.edu" <colins@mit.edu>,
"hmgr@mit.edu" <hmgr@mit.edu>, "danrod@MIT.EDU" <danrod@mit.edu>,
"mwhelan@mit.edu" <mwhelan@mit.edu>,
"k_brown@MIT.EDU" <k_brown@mit.edu>
CC: "joday@mit.edu" <joday@mit.edu>
Date: Fri, 31 May 2013 09:53:12 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEF89601@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved air handlers 1 through 5 shutdown for Bldg. NW35 - All, on Wednesday, June 5, 2013 through Friday, June 7, 2013, 9:00am - 2:45pm, per schedule below, is for your information. Any questions, please contact Jim O'Day, x5-4156.
Schedule:
Wednesday, June 5; 9:00am - 2:00pm; Air Handler 1, Area affected: 1st Floor, Room 1065B, and pub
Thursday, June 6; 9:00am - 11:45am; Air Handler 2, Area affected: 2nd Floor
Thursday, June 6; 12:30pm - 2:45pm; Air Handler 3, Area affected: 3rd Floor
Friday, June 7; 9:00am - 11:45am; Air Handler 4, Area affected: 4th Floor
Friday, June 7; 12:30pm - 2:45pm; Air Handler 5, Area affected: 5th Floor
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: June 5, 2013
Day: Wednesday
Time: 9:00am - 2:45pm per schedule
Building(s): NW35
Room(s): All (per schedule)
System: Air Handlers 1 through 5
Duration: 3 days, 5-6 hours/day per schedule
Reason:
Preventive maintenance
Effect:
Loss of supply ventilation, cooling, and heating air for the duration of the shutdown.