[169580] in Hotline Meeting
Approved - Bldg.35-4th floor Compressed Air/Vacuum shutdown
daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Wed May 22 11:22:00 2013
From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: "oconaill@mit.edu" <oconaill@mit.edu>, "DICKP@MIT.EDU" <DICKP@mit.edu>,
"alz@MIT.EDU" <alz@mit.edu>,
OPS RM Campus Services Main <rm-mcs@mit.edu>,
"lmcgon@mit.edu" <lmcgon@mit.edu>, "icuevas@mit.edu" <icuevas@mit.edu>,
"ktanaka@mit.edu" <ktanaka@mit.edu>,
"culpepper@mit.edu" <culpepper@mit.edu>,
"davidrod@mit.edu" <davidrod@mit.edu>,
"sbghosh@MIT.EDU" <sbghosh@mit.edu>, "maxine@mit.edu" <maxine@mit.edu>,
"bpant@mit.edu" <bpant@mit.edu>,
"MIT
Schedules Office" <schedules@mit.edu>
CC: "bdrink@mit.edu" <bdrink@mit.edu>, "plyons@mit.edu" <plyons@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
"cp-command@mit.edu"
<cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
Operators
<Operators@plant.mit.edu>,
DOF Customer Service Center <dof-csc@mit.edu>,
"Ops RM Shutdown" <rm-shutdown@mit.edu>,
Gary Saffie <gsaffie@plant.mit.edu>,
"Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>
Date: Wed, 22 May 2013 11:21:53 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEC95308@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Compressed Air/Vacuum shutdown for Bldg. 35-4th floor on Friday, May 24, 2013 is for your information. Any questions please contact Paul Lyons x3-5721.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938
Type: Normal
Date: May 24, 2013
Day: Friday
Time: 7:00am - 3:00pm
Building(s): 35
Room(s): 4th floor
System: Compressed Air/Vacumm
Duration: 8 hrs
Reason:
Preventative Maintenance of compressor & vacumm pump.
Effect:
Loss of compress air & lab vacuum.