[169579] in Hotline Meeting
Approved Bldg. 57 - All, Normal Building Power Shutdown
daemon@ATHENA.MIT.EDU (Janine Findlay)
Wed May 22 11:06:19 2013
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "elder@MIT.EDU" <elder@mit.edu>, "heinl@mit.edu" <heinl@mit.edu>,
"djmartin@mit.edu" <djmartin@mit.edu>,
"tmertz@mit.edu" <tmertz@mit.edu>,
"gillooly@MIT.EDU" <gillooly@mit.edu>,
"k_brown@MIT.EDU" <k_brown@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
Ops RM Electrical Controls Team <rm-elecctl@mit.edu>,
"dcrovo@mit.edu" <dcrovo@mit.edu>, "wscott@mit.edu" <wscott@mit.edu>,
"Ops
RM Shutdown" <rm-shutdown@mit.edu>,
"cp-command@mit.edu"
<cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
Operators
<Operators@plant.mit.edu>,
"DOF Customer Service Center" <dof-csc@mit.edu>,
"Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>
CC: "ajsilva@mit.edu" <ajsilva@mit.edu>, "rlucas@mit.edu" <rlucas@mit.edu>
Date: Wed, 22 May 2013 11:06:10 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEC952E0@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved normal building power shutdown for Bldg. 57 - All, on Thursday, May 23, 2013, 5:00am - 9:00am, is for your information. Any questions, please contact Joe Silva, x3-1602.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-1602
Type: Normal
Date: May 23, 2013
Day: Thursday
Time: 5:00am - 9:00am
Building(s): 57
Room(s): All
System: Normal Building Power
Duration: 4 hours
Reason:
repair 100 amp breaker in basement feed panel and perform preventive maintenance on switch gear
Effect:
Loss of normal building power for the duration of the shutdown.