Approved - Bldg. E23-1st floor Urgent Care Normal Building Power

daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Wed May 22 08:56:13 2013

From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: OPS RM Campus Services East <rm-ecs@mit.edu>,
        "Ops Custodial Admin &
 Support Staff" <cust-staff@mit.edu>,
        "bengel@mit.edu" <bengel@mit.edu>, "tquinn@mit.edu" <tquinn@mit.edu>,
        "brig@med.mit.edu" <brig@med.mit.edu>,
        "fris@med.mit.edu" <fris@med.mit.edu>,
        "heatherg@mit.edu" <heatherg@mit.edu>
CC: "bdrink@mit.edu" <bdrink@mit.edu>,
        "shutdowns@mit.edu"
	<shutdowns@mit.edu>,
        "sgilliga@mit.edu" <sgilliga@mit.edu>,
        "whomeyer@mit.edu" <whomeyer@mit.edu>,
        "cp-command@mit.edu"
	<cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>,
        Operators
	<Operators@plant.mit.edu>,
        DOF Customer Service Center <dof-csc@mit.edu>,
        "Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>,
        Karen Semerjian
	<ksemerj@plant.mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>
Date: Wed, 22 May 2013 08:56:08 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEC95153@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved Normal Building Power shutdown for Bldg. E23-1st flr Urgent Care on Friday, May 24, 2013 is for your information. Any questions please contact Billy Homeyer x8-0432. 

Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938

We request a bldg E23-1st floor Urgent Care panel P-1 normal bldg power shutdown from 3 AM to 5 AM on Friday, May 24th, 2013 for Crocker Electric to tie-into three existing spares (7, 9, 11) for pharmacy dispensing area receptacles and as part of the E23 pharmacy storefront project by Elaine Construction (Bernie Cincotta 617-590-3944). Kim Sutherland 8-5962 and Biss Teelucksingh 2-5972 are the MIT project managers.

Effects; general, reception and exam room dedicated circuits; Urgent Care lighting; security camera; electric wall heaters; copy machine; automatic doors. Emergency power remains unaffected. 


Type: Normal
Date: May 24, 2013
Day: Friday
Time: 3:00am - 5:00am
Building(s): E23
Room(s): 1st floor 
System: Normal Bldg. Power
Duration: 2 hours
Reason: 
To tie in power to recepticles in the pharmacy dispensing area.

Effect: 
Loss of power.
 