Bldgl. E23-1st floor Urgent Care Shutdown Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue May 21 15:22:40 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <bdrink@MIT.EDU>, <shutdowns@MIT.EDU>, <sgilliga@MIT.EDU>,
        <whomeyer@MIT.EDU>
Date: Tue, 21 May 2013 15:22:37 -0400
Message-ID: <8247962AAFC24F14B10AD7C087C14D82@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Normal Building Power shutdown request for Bldg. E23-1st flr Urgent Care on Friday, May 24, 2013 is for your information and response. Any questions please contact Billy Homeyer x8-0432. 

Would you please let us know whether this does or does not have your approval.

Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938

We request a bldg E23-1st floor Urgent Care panel P-1 normal bldg power shutdown from 3 AM to 5 AM on Friday, May 24th, 2013 for Crocker Electric to tie-into three existing spares (7, 9, 11) for pharmacy dispensing area receptacles and as part of the E23 pharmacy storefront project by Elaine Construction (Bernie Cincotta 617-590-3944). Kim Sutherland 8-5962 and Biss Teelucksingh 2-5972 are the MIT project managers.

Effects; general, reception and exam room dedicated circuits; Urgent Care lighting; security camera; electric wall heaters; copy machine; automatic doors. Emergency power remains unaffected. 


Type: Normal
Date: May 24, 2013
Day: Friday
Time: 3:00am - 5:00am
Building(s): E23
Room(s): 1st floor 
System: Normal Bldg. Power
Duration: 2 hours
Reason: 
To tie in power to recepticles in the pharmacy dispensing area.

Effect: 
Loss of power.