[169231] in Hotline Meeting
Bldg. E19-4th fl. Mech rm/6th & 7th fls. (IS&T) (E17/E18 backfill project) . Heating Hot Water Shutdown
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue May 14 08:17:25 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <plyons@MIT.EDU>, <jcollins@MIT.EDU>
Date: Tue, 14 May 2013 08:17:14 -0400
Message-ID: <D04C0BF760C84040BF158B8108662EA7@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Heating Hot Water Shutdown is for bldg. E19-4th fl. mech rm on Saturday, May 18, 2013 from 6:00am til 3:00pm is for your information and approval. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: May 18, 2013
Day: Saturday
Time: 6:00am - 3:00pm
Building(s): E19
Room(s): 4th fl. mech rm, 6th & 7th fls. (IS&T) (E17/E18 backfill project)
System: heating hot water
Duration: 6:00am - 3:00pm
Reason:
We request a bldg E19-4th floor mech room heating hot water shutdown (will affect 6th & 7th floors/IS&T) at 6 AM to 3 PM on Saturday, May 18th, 2013 to demo abandoned pumps as part of the E17/E18 backfill project by Barr and Barr Builders (Dick Akins 774-281-0162). Joe Collins 3-3621 and Jan Burke 8-5463 are the MIT project managers on behalf of Billy Homeyer
Effect:
Loss of heating hot water for the duration of this shutdown.