Bldg. 2 - basement Chilled Water Shutdown (NOTE: comfort cooling will be down for duration)

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri May 10 07:32:52 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <mdeluga@MIT.EDU>
Date: Fri, 10 May 2013 07:32:46 -0400
Message-ID: <5F396F1D505642A1A67A18AB9B8C641A@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Chilled Water Shutdown is for bldg. 2 - basement (NOTE: comfort cooling will be down for duration) is on Saturday, May 11, 2013 from 6:00am - 4:00pm is for your information and approval.  Any questions please contact Billy Homeyer x8-0432.


Would you please let us know if this does or does not have your approval.


Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: May 11, 2013
Day: Saturday
Time: 6:00am - 4:00pm
Building(s): 2
Room(s): basement
System: chilled water
Duration: 6:00am - 4:00pm
Reason: 
We request a bldg 2-bsmt chilled water shutdown from 6 AM to 4 PM on Saturday, May 11th, 2013 to tie-in new construction area chilled water risers - (NOTE: there will be no chilled water to lab processed chilled water system from 6 AM to 7 AM and comfort cooling will be down for the duration of the shutdown) as part of the 2-Chemistry renovation project by Bond Brothers (Jesse Conklin 617-938-4175).  Marty Deluga 4-5081 and Joe Collins 3-3631 are the project managers on behalf of Billy Homeyer.

Effect: 
Loss of chilled water and comfort cooling for the duration of this shutdown. 