Approved - Bldg. E18-509,566,566A - Normal Building Power Shutdown

daemon@ATHENA.MIT.EDU (Jennifer Garland)
Mon May 6 12:58:27 2013

From: Jennifer Garland <jennygar@plant.mit.edu>
To: "nsteele@mit.edu" <nsteele@mit.edu>,
        "barreiro@mit.edu"
	<barreiro@mit.edu>,
        "jmganno@MIT.EDU" <jmganno@mit.edu>, "vang@mit.edu"
	<vang@mit.edu>,
        OPS RM Campus Services East <rm-ecs@mit.edu>,
        Ops RM All
	<rm-org@mit.edu>, "tquinn@mit.edu" <tquinn@mit.edu>,
        "heatherg@mit.edu"
	<heatherg@mit.edu>,
        "shutdowns@mit.edu" <shutdowns@mit.edu>,
        "plyons@mit.edu"
	<plyons@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>, DOF EHS
	<dof-ehs@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        "DOF
 Customer Service Center" <dof-csc@mit.edu>,
        "Ops Custodial Admin & Support
 Staff" <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>,
        "sgilliga@mit.edu"
	<sgilliga@mit.edu>
Date: Mon, 6 May 2013 12:58:17 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AD0B58B5@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved Normal Building Power Shutdown is for bldg. E18 - 509,566,566A on Tuesday, May 7, 2013 from 4:00am - 7:00am is for your information.  Any questions please contact Steve Gilligan x3-8079.



Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: May 7, 2013
Day: Tuesday
Time: 4:00am - 7:00am
Building(s): E18
Room(s): 509,566,566A
System: panel P5D2,building power, exhaust laboratory
Duration: 4:00am - 7:00am
Reason: 
This is to install new electrical circuit in this panel.  

Effect: 
Loss of building power for the duration of this shutdown. 