Approved - Bldg. E15-015,016,023,023A,039,040 (015 Lab entryway

daemon@ATHENA.MIT.EDU (Jennifer Garland)
Mon May 6 12:44:44 2013

From: Jennifer Garland <jennygar@plant.mit.edu>
To: Jim Harrington <lordjim@mit.edu>,
        "cohen@MEDIA.MIT.EDU"
	<cohen@media.mit.edu>,
        OPS RM Campus Services East <rm-ecs@mit.edu>,
        "freilach@mit.edu" <freilach@mit.edu>,
        "kdavis@MEDIA.MIT.EDU"
	<kdavis@media.mit.edu>,
        "glt@media.mit.edu" <glt@media.mit.edu>,
        "shutdowns@mit.edu" <shutdowns@mit.edu>,
        "whomeyer@mit.edu"
	<whomeyer@mit.edu>,
        "ksemerj@mit.edu" <ksemerj@mit.edu>,
        "sgilliga@mit.edu"
	<sgilliga@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>, DOF EHS
	<dof-ehs@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        "DOF
 Customer Service Center" <dof-csc@mit.edu>,
        "Ops Custodial Admin & Support
 Staff" <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>, "pisanin@mit.edu" <pisanin@mit.edu>
Date: Mon, 6 May 2013 12:44:31 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AD0B5894@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved Normal Electrical 120V/208V Building Power Shutdown is for bldg. E15-015,016,023,023A,039,040 (015 Lab entryway project) on Tuesday, May 7, 2013 from 1:00pm - 3:00pm is for your information.  Any questions please contact Billy Homeyer x8-0432.



Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: May 7, 2013
Day: Tuesday
Time: 1:00PM - 3:00PM
Building(s): E15
Room(s): 015,016,023,023A,039,040 (015 Lab entryway project)
System: Normal Electrical 120V/208V Building Power 
Duration: 1:00PM - 3:00PM
Reason: 
We request a bldg E15-023 lab power panel RP1 normal 208V/120V power shutdown from 1 PM to 3 PM on Tuesday afternoon, May 7th, 2013 for MacNichol Electric (Jesse Pothier 617-592-9427) to replace the 4 gage wiring between panels RP1 in 023 and RP1A in 015 with 1 gage wiring and also to install additional circuit breakers in panel RP1A for some new lab equipment/freezer and as part of the E15-015 entryway project by Acella Construction (Scott Brash 781-812-6066). Sudy Nally 8-8010 and Nicole Pisani 5-5157 are the MIT project managers.

All power in labs E15-015, 016, 023/023A, 039 and 040 will be affected. 


Effect: 
Loss of normal building power for the duration of this shutdown.  