CANCELLED - Bldg. 18-509,566, 566A - Electrical Power Shutdown
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Fri May 3 12:44:58 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: "jdoughty@mit.edu" <jdoughty@mit.edu>, "swade@mit.edu" <swade@mit.edu>,
"rjwilk@mit.edu" <rjwilk@mit.edu>,
OPS RM Campus Services East
<rm-ecs@mit.edu>,
Ops CSG All <csg-all@mit.edu>, "scottide@MIT.EDU"
<scottide@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>,
"sgilliga@mit.edu"
<sgilliga@mit.edu>
Date: Fri, 3 May 2013 12:44:51 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AD0B527B@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following CANCELLED Electrical Power Shutdown is for bldg. 18 - rm. 509,566, 566A is on Tuesday, May 7, 2013 from 4:00am - 7:00am is for your information. Any questions please contact Steve Gilligan x3-8079.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: May 7, 2013 //// CANCELLED
Day: Tuesday
Time: 4:00am - 7:00am///CANCELLED
Building(s): 18
Room(s): 509,566, 566A
System: electrical power/exhaust laboratory
Duration: 4:00am - 7:00am - 3 hrs
Reason:
This is to install new circuits to electrical panel.
Effect:
Loss of electrical power for the duration of this shutdown.