[168794] in Hotline Meeting
Approved - Bldg. 68 - Elevator #1 Shutdown --- ** DATES CHANGED:
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Thu May 2 09:22:37 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: "jfucillo@mit.edu" <jfucillo@mit.edu>,
"jmganno@MIT.EDU"
<jmganno@mit.edu>,
"macdonaj@mit.edu" <macdonaj@mit.edu>,
"OPS RM Campus
Services East" <rm-ecs@mit.edu>,
Ops Custodial Admin & Support Staff
<cust-staff@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"Ams99@mit.edu"
<Ams99@mit.edu>,
"kasabula@mit.edu" <kasabula@mit.edu>,
"ksimons@mit.edu"
<ksimons@mit.edu>,
"rwong@brighthorizons.com" <rwong@brighthorizons.com>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
"plyons@mit.edu" <plyons@mit.edu>,
"joe.gaspar@us.schindler.com" <joe.gaspar@us.schindler.com>,
Ops RM Shutdown
<rm-shutdown@mit.edu>, DOF EHS <dof-ehs@mit.edu>,
"cp-command@mit.edu"
<cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
Operators
<Operators@plant.mit.edu>,
DOF Customer Service Center <dof-csc@mit.edu>,
"Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>,
"mgiambro@mit.edu"
<mgiambro@mit.edu>
Date: Thu, 2 May 2013 09:22:29 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13ACBBE670@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Elevator #1 Shutdown is for Bldg. 68 on Friday, May 3, 2013 from 7:00am - 11:00am is for your information. Any questions please contact Mike Giambrone x3-6353.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: May 3, 2013
Day: Friday
Time: 7:00am - 11:00am
Building(s): 68
Room(s): bldg.
System: Elevator #1
Duration: 7:00am - 11:00am 4 hrs
Reason:
This is to make repairs to railings in cab of elevator.
Effect:
Loss of use of Elevator for the duration of this shutdown. Signs will be posted.