[168780] in Hotline Meeting
Bldg. 9. All - Fire Alarm Shutdown w/*live audible 1st/3rd party testing*
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu May 2 08:26:12 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <jcombs@MIT.EDU>
Date: Thu, 2 May 2013 08:26:08 -0400
Message-ID: <5B8EDD0CED90455C8D85D7FF5EE84867@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Fire Alarm Shutdown w/*live audible 1st/3rd party testing is for bldg. 9 - All on Monday, May 6, 2013 til Tuesday, May 7, 2013 from 6:00am til 7:30am is for your information and approval. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: May 6, 2013
Day: Monday
Time: 6:00am - 7:30am
Building(s): 9
Room(s): All
System: Fire Alarm
Duration: 6:00am - 7:30am
Reason:
We request bldg 9-all fire alarm shutdowns at 6 AM to 7:30 AM on Monday, May 6th and Tuesday, May 7th, 2013 for Reilly Electric (Bob Bedard 508-962-1804) to change the speaker settings on the lobby speaker/strobes in order to alleviate a feedback problem on the microphone and to conduct *live audible 1st/3rd party testing on both days of the bldg 9 fire alarm system* as part of the bldg 9 fire alarm system upgrade project by Elaine Construction (Nick Murray 617-799-7913). Joe Collins 3-3621 and Jennifer Combs 3-7671 are the MIT project managers on behalf of Billy Homeyer.
Effect:
Loss of fire alarms for the duration of this shutdown.