[168779] in Hotline Meeting
Bldg. 3-166, fire protection water, shutdown notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu May 2 08:03:35 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <sinanig@MIT.EDU>
Date: Thu, 2 May 2013 08:03:25 -0400
Message-ID: <CE34B703E957497A912520078322898D@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following fire protection water system, shutdown notification for building 3-166 (Prof. Lienhard's office renovation project) on Friday, May 3, 2013 from 6:00 am to 9:00 am is for your information. No response is required to this notification. Any questions, please contact Billy Homeyer ext. 8-0432.
We appreciate your patience while the repairs/renovations are in progress.
Thank you
Nicole McKenna
Operations Center
Type: Normal
Date: May 3, 2013
Day: Friday
Time: 6:00am - 9:00am
Building(s): 3
Room(s): 166
System: fire protection water
Duration: 3 hours
Reason:
to tie in four new sprinkler heads from 2nd branch in the hallway
Effect:
loss of fire protection water