[168668] in Hotline Meeting
Bldg. 46-1st fllor/1150, 1152 (McGovern tesla MRI), smoke detector system, shutdown notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Apr 29 13:01:37 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <sudy@mit.edy>
Date: Mon, 29 Apr 2013 13:01:26 -0400
Message-ID: <41DA7CF74386457C99C8FAF823CB2F71@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following smoke detector system shutdown notification for building 46-1st floor/1150, 1152 (McGovern tesla MRI) on Tuesday, April 30, 2013 through Friday, May 31, 2013 from 4:00am - 2:00pm each (regular work) day is for your information. No response is required to this notification. Any questions, please contact Billy Homeyer ext 8-0432.
We appreciate your patience while the repairs/renovations are in progress.
Thank you.
Nicole McKenna
Operations Center
Type: Normal
Date: April 30, 2013
Day: Tuesday
Time: 4:00 AM - 2:00 PM
Building(s): 46
Room(s): 1st floor/1150, 1152 (McGovern tesla MRI)
System: smoke detector system
Duration: 10 hours each day
Reason:
for construction dust and all general construction related activities
Effect: