[168667] in Hotline Meeting
Bldg. E23-1st floor, fire protection water system, shutdown notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Apr 29 12:35:50 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <biss@MIT.EDU>
Date: Mon, 29 Apr 2013 12:35:44 -0400
Message-ID: <BE2E397F9E1C4B22AF40EB84742C7D80@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following fire protection water system shutdown notification for building E23-1st floor on Wednesday, May 1, 2013 at 6:00pm through Thursday morning at 4:00am and again on Thursday, May 2, 2013 at 6:00pm through Friday morning at 4:00am is for your information. No response is required to this notification. Any questions please contact Billy Homeyer ext. 8-0432.
We appreciate your patience while the repairs/renovations are in progress.
Thank you.
Nicole McKenna
Operations Center
Type: Normal
Date: May 1, 2013
Day: Wednesday
Time: 6:00pm
Building(s): E23
Room(s): 1st floor
System: Fire protection water
Duration: 10 hours each day
Reason:
to drain sprinklers during demolition and sprinkler work
Effect:
Loss of fire protection water