[160728] in Hotline Meeting
Approved Bldg. 10 - All, Natural Gas and Domestic Hot and Cold
daemon@ATHENA.MIT.EDU (Janine Findlay)
Thu Aug 2 13:06:21 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
"whomeyer@mit.edu"
<whomeyer@mit.edu>,
Ops RM Plumbing Team <rm-plumbing@mit.edu>,
"Ops RM
Shutdown" <rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@mit.edu>,
"Ops Custodial Admin & Support
Staff" <cust-staff@mit.edu>,
Jim Harrington <lordjim@mit.edu>, "laugh@mit.edu" <laugh@mit.edu>,
"jgk@mit.edu" <jgk@mit.edu>, "joels@mit.edu"
<joels@mit.edu>,
OPS RM Campus Services Main <rm-mcs@mit.edu>,
"Ops
Custodial Admin & Support Staff" <cust-staff@mit.edu>,
"dugan@mit.edu"
<dugan@mit.edu>, "gearin@mit.edu" <gearin@mit.edu>,
"segaloff@MIT.EDU"
<segaloff@mit.edu>,
"jschuler@mit.edu" <jschuler@mit.edu>,
"sgass@mit.edu"
<sgass@mit.edu>, "dgeraci@mit.edu" <dgeraci@mit.edu>,
Michael Smith
<masmith@mit.edu>, "willer@mit.edu" <willer@mit.edu>,
"awolpert@mit.edu"
<awolpert@mit.edu>,
"herrickd@MIT.EDU" <herrickd@mit.edu>,
"jdurant@mit.edu"
<jdurant@mit.edu>, "mleen@mit.edu" <mleen@mit.edu>,
"dstidsen@mit.edu"
<dstidsen@mit.edu>,
"carleton@mit.edu" <carleton@mit.edu>,
"jdennis@MIT.EDU"
<jdennis@mit.edu>,
"gillooly@MIT.EDU" <gillooly@mit.edu>,
"esdeb@mit.edu"
<esdeb@mit.edu>,
"emmarogers@mit.edu" <emmarogers@mit.edu>,
"annm@mit.edu"
<annm@mit.edu>, "alexnow@mit.edu" <alexnow@mit.edu>,
"kates@mit.edu"
<kates@mit.edu>, "wayneb@mit.edu" <wayneb@mit.edu>,
MIT Schedules Office
<schedules@mit.edu>,
"vdavenport@MIT.EDU" <vdavenport@mit.edu>,
"barnard@mit.edu" <barnard@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
"kyegian@MIT.EDU" <kyegian@mit.edu>
CC: "jcombs@mit.edu" <jcombs@mit.edu>
Date: Thu, 2 Aug 2012 13:06:16 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CEB7C3E99@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved natural gas and domestic hot and cold water shutdown for Bldg. 10 - All, on Friday, August 3, 2012, 5:00am - 7:30am, is for your information. Any questions, please contact Billy Homeyer, x8-0432.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: August 3, 2012
Day: Friday
Time: 5:00am - 7:30am
Building(s): 10
Room(s): All
System: Natural Gas and Domestic Hot and Cold Water
Duration: 2.5 hours
Reason:
We request bldg 10-all natural gas and domestic water shutdown from 5 AM to 7:30 AM on Friday, August 3rd to tie-in the new stove and dw to tie-in the new sink as part of the 10-320 kitchen renovation/exhaust system upgrade project by Shawmut Construction (Paul McGee 61-839-0412/Dick O'Connell 617-839-6186). Jennifer Combs 3-7671 is the MIT project manager.
Effect:
Loss of domestic hot and cold water and natural gas for the duration of the shutdown.