Approved Bldg. E17 - All, Lab Process Hot and Cold Water Shutdown

daemon@ATHENA.MIT.EDU (Janine Findlay)
Fri Jul 20 14:21:52 2012

From: Janine Findlay <jfindlay@plant.mit.edu>
To: Ops RM Plumbing Team <rm-plumbing@MIT.EDU>,
        "shutdowns@mit.edu"
	<shutdowns@MIT.EDU>,
        Billy Homeyer <whomeyer@plant.mit.edu>,
        Ops RM Shutdown
	<rm-shutdown@MIT.EDU>,
        "cp-command@mit.edu" <cp-command@MIT.EDU>,
        "safety@mit.edu" <safety@MIT.EDU>, Operators <Operators@plant.mit.edu>,
        "DOF
 Customer Service Center" <dof-csc@MIT.EDU>,
        "Ops Custodial Admin & Support
 Staff" <cust-staff@MIT.EDU>,
        "bbrown@mit.edu" <bbrown@MIT.EDU>, "jmganno@MIT.EDU" <jmganno@MIT.EDU>,
        "jstatile@mit.edu" <jstatile@MIT.EDU>, "vang@mit.edu" <vang@MIT.EDU>,
        OPS RM Campus Services East <rm-ecs@MIT.EDU>,
        Ops Custodial Admin & Support Staff <cust-staff@MIT.EDU>,
        "graposa@MIT.EDU"
	<graposa@MIT.EDU>,
        "heatherg@mit.edu" <heatherg@MIT.EDU>,
        "barnard@mit.edu"
	<barnard@MIT.EDU>,
        "monaglek@MIT.EDU" <monaglek@MIT.EDU>,
        "tquinn@mit.edu"
	<tquinn@MIT.EDU>
CC: "jcollins@mit.edu" <jcollins@MIT.EDU>
Date: Fri, 20 Jul 2012 14:21:48 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CEB53CECE@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved lab process hot and cold water shutdown for Bldg. E17 - All, on Monday, July 23, 2012, 6:00am through 2:00pm on Wednesday, July 25, 2012, is for your information.  Any questions, please contact Billy Homeyer, x8-0432.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Normal
Date: July 23, 2012
Day: Monday
Time: 6:00am (7/23) - 2:00pm (7/25)
Building(s): E17
Room(s): All
System: Lab Process Hot and Cold Water
Duration: 56 hours
Reason: 
We request a bldg E17-all lab process hot/cold water shutdown from 6 AM on Monday, July 23rd to 2 PM on Wednesday, July 25th, 2012 for American Plumbing/Heating to demo glass lab waste piping in the south east stairwell and tie-in to a new acid resistant piping run as part of the E17/E18 backfill project by Barr and Barr Builders (Dick Akins 774-281-0162). Joe Collins 3-3621 and Jan Burke are the MIT project managers.

Effect: 
Loss of lab process hot and cold water for the duration of the shutdown.