Bldg. 48 - 4th Floor, Chilled Water Shutdown Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue Jul 17 13:54:54 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <sudy@MIT.EDU>
Date: Tue, 17 Jul 2012 13:54:50 -0400
Message-ID: <3FD4122822CB446FBCA652459846D56C@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following chilled water shutdown request for Bldg. 48 - 4th Floor, on Thursday, July 19, 2012, 12:30pm - 1:30pm, is for your information and response.  Any questions, please contact Billy Homeyer, x8-0432.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Normal
Date: July 19, 2012
Day: Thursday
Time: 12:30pm - 1:30pm
Building(s): 48
Room(s): 4th Floor
System: Chilled Water
Duration: 1 hour
Reason: 
We request a bldg 48-4th floor chilled water shutdown from 12:30 PM to 1:30 PM on Thursday afternoon, July, 19th, 2012 for AHC Mechanical (Guy Fossiano 781-844-7815) to cut/cap at mains, chilled water service to a 48-434 fcu being demo'd as part of the Prof Polz Lab renovation project by Elaine Construction (Bill Kelly 781-974-2195). Sudy Nally 8-8010 and Jennifer Combs 3-7671 are the MIT project managers.

Note* Harris will be on-site at 12:30 PM to switch the cold rooms condensers over to city water cooling (Steve Roberts 978-479-7021)


Effect: 
Loss of chilled water, condenser water, and supply cooling air for the duration of the shutdown.