[160083] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Approved - W71 - All Emergency & Normal Power shutdown

daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Thu Jul 12 13:52:57 2012

From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: "tommyl@mit.edu" <tommyl@mit.edu>, "myersm@MIT.EDU" <myersm@mit.edu>,
        "OPS RM Campus Services West" <rm-wcs@mit.edu>,
        "src@MIT.EDU" <src@mit.edu>, "hmgr@mit.edu" <hmgr@mit.edu>,
        "kcn@mit.edu" <kcn@mit.edu>, "mwhelan@mit.edu"
	<mwhelan@mit.edu>
CC: "shutdowns@mit.edu" <shutdowns@mit.edu>,
        Billy Homeyer
	<whomeyer@plant.mit.edu>,
        "sgilliga@mit.edu" <sgilliga@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        DOF Customer Service Center
	<dof-csc@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>,
        "Ops RM Electrical
 Controls Team" <rm-elecctl@mit.edu>
Date: Thu, 12 Jul 2012 13:52:54 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CEADE40FA@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved Emergency & Normal Power shutdown for Bldg. W71-All on Friday, July 13, 2012 is for your information. Any questions, please contact Billy Homeyer x8-0432.

Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938

We request bldg W71-all normal and emergency power shutdowns on Friday, July 13th, 2012 as follows; emergency power from 6 AM to 10 AM for J. & M. Brown Co (Bob Cataldo 617-592-1564) to remove the emergency power feed to the auto transfer switch and install a new emergency power panel for life-safety/fire alarm systems; and a bldg all normal power shutdown from 1 PM to 2 PM for JMBCo to remove the normal power feed to the ATS and remove the fire pump feed which is tapped off the buss between the 13.8KV-480V transformer and the substation main (fire pump is being demo'd - system gets fed from west campus fire main) and as part of the bldg W71 life-safety upgrades project by Shawmut Construction (Tom Ploude 781-983-3850), Keith Diggans 4-6174 is the MIT project manager, John Engle 4-5001 is covering.

Type: Normal
Date: July 13, 2012
Day: Friday
Time: 6:00am 10:00am (emerg) 1:00pm - 2:00pm (normal)
Building(s): W71
Room(s): All
System: Emergency Power and Normal Power
Duration: 4 hours (emerg) 1 hours (normal
Reason: 
To demo the generator/fire pump auto transfer switch, demo the fire pump.

Effect: 
Loss of emergency power 6:00am - 10:00am and loss of normal power 1:00pm - 2:00pm.
 