[160081] in Hotline Meeting
Building 37-bsmt/5th and 6th floors smoke detector shutdown notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jul 12 12:54:23 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <sinanig@MIT.EDU>
Date: Thu, 12 Jul 2012 12:54:17 -0400
Message-ID: <E10816621A59437D8E29319477B896DA@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following smoke detector shutdown notification for Bldg. 37-bsmt 5th /6th floor on Friday, July 13, 2012 through Friday, August 10, 2012 from 6am to 2pm is for your information. No response is required to this notification. Any questions please contact Billy Homeyer at 8-0432.
We appreciate your patience while the repairs/renovations are in progress.
Thank you,
Linda Bradford
Operation Center
Type: Normal
Date: July 13, 2012
Day: Friday
Time: 6am
Building(s): Bldg. 37
Room(s): bsmt, 5th and 6th floor
System: Smoke detectors
Duration: 8 hours each day
Reason:
We request bldg 37-bsmt/5th/6th floor smoke detector shutdowns from 6 AM to 2 PM each regular work day between Friday, July 13th and Friday, August 10th, 2012 for construction dust associated with the 37-6th floor office suite renovation project.
Effect:
loss of smoke detectors