[160069] in Hotline Meeting
RE: W71 - All Emergency & Normal Power shutdown request
daemon@ATHENA.MIT.EDU (Marsha Whelan)
Thu Jul 12 10:08:12 2012
From: Marsha Whelan <mwhelan@MIT.EDU>
To: "shutdown-response@MIT.EDU" <shutdown-response@MIT.EDU>,
"undisclosed_recipients@mit.edu" <undisclosed_recipients@MIT.EDU>
CC: "shutdowns@mit.edu" <shutdowns@MIT.EDU>,
"whomeyer@plant.mit.edu"
<whomeyer@plant.mit.edu>,
Steven R Gilligan <sgilliga@MIT.EDU>
Date: Thu, 12 Jul 2012 14:08:04 +0000
Message-ID: <16A97110DF88C54ABD8202095E8D35E12A6F04CF@OC11EXPO31.exchange.mit.edu>
In-Reply-To: <65F1910EACD5482B94268BF04C436607@facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
Approved from Housing.
-----Original Message-----
From: shutdown-response@MIT.EDU [mailto:shutdown-response@MIT.EDU]
Sent: Thursday, July 12, 2012 10:03 AM
To: undisclosed_recipients@mit.edu
Cc: shutdowns@mit.edu; whomeyer@plant.mit.edu; Steven R Gilligan
Subject: W71 - All Emergency & Normal Power shutdown request
Importance: High
The following Emergency & Normal Power shutdown request for Bldg. W71-All on Friday, July 13, 2012 is for your information and response. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know whether this does or does not have your approval.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938
We request bldg W71-all normal and emergency power shutdowns on Friday, July 13th, 2012 as follows; emergency power from 6 AM to 10 AM for J. & M. Brown Co (Bob Cataldo 617-592-1564) to remove the emergency power feed to the auto transfer switch and install a new emergency power panel for life-safety/fire alarm systems; and a bldg all normal power shutdown from 1 PM to 2 PM for JMBCo to remove the normal power feed to the ATS and remove the fire pump feed which is tapped off the buss between the 13.8KV-480V transformer and the substation main (fire pump is being demo'd - system gets fed from west campus fire main) and as part of the bldg W71 life-safety upgrades project by Shawmut Construction (Tom Ploude 781-983-3850), Keith Diggans 4-6174 is the MIT project manager, John Engle 4-5001 is covering.
Type: Normal
Date: July 13, 2012
Day: Friday
Time: 6:00am 10:00am (emerg) 1:00pm - 2:00pm (normal)
Building(s): W71
Room(s): All
System: Emergency Power and Normal Power
Duration: 4 hours (emerg) 1 hours (normal
Reason:
To demo the generator/fire pump auto transfer switch, demo the fire pump.
Effect:
Loss of emergency power 6:00am - 10:00am and loss of normal power 1:00pm - 2:00pm.