[160068] in Hotline Meeting
RE: W34/ W35 HIgh Pressure Steam, Hot Water, Condensate Return
daemon@ATHENA.MIT.EDU (Daniel Martin)
Thu Jul 12 10:03:25 2012
From: Daniel Martin <djmartin@MIT.EDU>
To: "shutdown-response@MIT.EDU" <shutdown-response@MIT.EDU>,
"undisclosed_recipients@mit.edu" <undisclosed_recipients@MIT.EDU>
CC: "shutdowns@mit.edu" <shutdowns@MIT.EDU>,
"vcrayton@plant.mit.edu"
<vcrayton@plant.mit.edu>,
"mmcorrie@mit.edu" <mmcorrie@MIT.EDU>,
"wscott@plant.mit.edu" <WScott@plant.mit.edu>,
"kmconnol@plant.mit.edu"
<kmconnol@plant.mit.edu>
Date: Thu, 12 Jul 2012 14:03:18 +0000
Message-ID: <17F5A479B2F16342A95B9694813937ED0A272F@OC11EXPO32.exchange.mit.edu>
In-Reply-To: <5089350B41194AF782D5EBCE6BC1EBF8@facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
To All,
Please make sure all systems are tested after work is completed. We have a major swim meet starting in the Z center Friday afternoon through the weekend.
Go Tech!
-----Original Message-----
From: shutdown-response@MIT.EDU [mailto:shutdown-response@MIT.EDU]
Sent: Thursday, July 12, 2012 8:56 AM
To: undisclosed_recipients@mit.edu
Cc: shutdowns@mit.edu; vcrayton@plant.mit.edu; mmcorrie@mit.edu
Subject: W34/ W35 HIgh Pressure Steam, Hot Water, Condensate Return shutdown request
Importance: High
The following high pressure steam shutdown request for Bldg. W34 & W35 on Thursday, July 12, 2012 is for your information and response.
Any questions, please contact Vaughn Crayton x3-5898.
Would you please let us know whether this does or does not have your approval.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938
Type: Normal
Date: July 12, 2012
Day: Thursday
Time: 9:30pm - 1:30am
Building(s): W34/W35
Room(s): All
System: High Pressure Steam, Hot Water, Condensate return
Duration: 4 hours
Reason:
To install a temporary steam feed to service W34 & W35.
Effect:
Loss of all pressure steam, heating, hot domestic, lab heating hot water.